Adams Elementary Together Spokane

Drivers on Spokane's South Hill have watched the new Adams Elementary rise from the ground, as crews are working hard to stay on time and on budget.

But while the new school is perhaps the most visible Together Spokane project, plenty of other projects in neighborhoods across the city are complete and in progress.

"This year saw the kickoff of the all-weather fields project, including construction starts at Shadle Park and Rogers," Superintendent Adam Swinyard shared with local media this week. "Planning is underway for North Central High School, the Merkel Sports Complex, the Madison Elementary Community Center, and Franklin Park. All-weather field construction will wrap up at Rogers and begin at Ferris and Lewis & Clark.

In Progress and Completed

Adams Elementary

Adams Elementary under construction

The new Adams Elementary is on budget and on time, slated to open at the start of the 2027-28 school year. The site design was intended to ensure parking and playground areas are shielded from the busy streets by the school building.

Shadle Park and Rogers All-Weather Fields

Softball field

Crews broke ground in the summer on all-weather football, baseball and softball infields at Shadle Park High School, and all-weather softball and baseball infields at Rogers High School. These projects are now complete, and students and the community are using them to their fullest extent. Whether it's high school, middle school or youth teams, the fields have already proven to be vital assets to Spokane's sports and recreation community.

Previously, the high school's grass fields went unused beginning in November because the weather turned them to mud. All-weather surfaces don't have that problem and extend the sports season, giving more kids and adults opportunities to be active and engaged with their peers. Lights are also installed at the Shadle all-weather football field, giving the public opportunities to extend the schedule into the night.


Coming Up

All-Weather Fields Phase 2

This coming April through October, all-weather fields will be installed at these locations:

  • Rogers High School (Football/Soccer)

  • Ferris High School (Football/Soccer, Softball and Baseball)

  • Hart Field, serving Lewis & Clark High School (Football/Soccer, Softball and Baseball)

  • Dwight Merkel Sports Complex (Football/Soccer)

The all-weather fields at the Dwight Merkel Sports Complex will be installed at the former Joe Albi Stadium site.

"The enlarged (Merkel) complex provides the scale needed to attract large regional youth and adult tournaments," Swinyard said. "This allows local families to stay home for competitions while bringing economic benefits to Spokane's hospitality and restaurant sectors."

Madison Elementary and Franklin Park

Park options 1 and 2

Madison Elementary and Franklin Park are managed by two different entities – SPS and Parks, respectively – and improvements of each are funded through approvals of two separate ballot items. But in keeping with the Together Spokane ethos, both projects are directly connected.

Madison Elementary borders Franklin Park, and students and their families use the park inside and outside of school hours.

Last winter and spring, SPS and the City of Spokane worked together to explore usage of space at Franklin Park for a Madison Elementary replacement. SPS and Parks are surveying the public on priorities for the park, as well as the possibility of placing the new Madison Elementary in a different area (it currently sits at the northwest corner of the park).

"This enables us to keep kids in Madison while we build the new school," SPS Chief Operating Officer Travis Schulhauser told the School Board. "We won't have to distribute students across other schools or find another spot for them. We can have them continue learning and growing in their school."

SPS entered a Progressive Design Build (PDB) process for Madison, which allows construction and material procurement to begin while design work is still underway rather than waiting for the full design process to finish. Lydig Construction and Integrus Architecture were selected as the PDB team. SPS has also held multiple input sessions with Madison staff and students, and Spokane Parks has done the same with members of the community around the future of Franklin Park.

"The power of this partnership is when we go through this design, we get to think about Madison a little differently," Schulhauser said. "The school we get to think about as a school, as a community center, as a fieldhouse, and how it sits in all of Franklin Park."

North Central High School

The modernization of North Central High School is in the planning stages and NAC, which was selected as the architect in March, is now in the design phase. Bouten Construction was selected as the general contractor, and we're continuing to work with leadership at North Central to learn about the needs of staff.

Garry and Chase Middle Schools

We're still in the early planning phase for Garry and Chase middle schools. ALSC has been selected as the architect for both buildings, and we will begin the search for a general contractor in early 2027.

Staff are currently defining the full scope of each project.


Visit TogetherSpokane.org to receive updates on projects happening across Spokane, including projects overseen by City of Spokane Parks and Recreation.

Watch SPS Chief Operating Officer Travis Schulhauser give a full Together Spokane update to the Spokane School Board: